RSD switch Additional Info
Installer Memo - North America     
2  © 2022 Enphase Energy Inc. All rights reserved.  May 13, 2022 
4.  How to verify the Rapid Shutdown (RSD) switch installation and functionality? 
Page  5  of  this  document  provides  the  procedure  to  verify  RSD  switch  installation  and 
functionality. 
5.  When to use the RSD switch with IQ System Controller 2? 
The RSD switch is required and must only be used for IQ8 microinverters. For systems with 
grid tied PV i.e., IQ6/7 or M215/250 microinverters, installers must not use the Rapid shutdown 
switch. Rapid Shutdown operation for these microinverters can be initiated in one of three 
ways 
a.  The AC circuit breaker installed within the IQ Combiner 
b.  Or the AC circuit breaker installed within IQ System Controller 
c.  Or a dedicated AC disconnect switch in series with the combined PV inverter circuit 
Installer  must  follow  all  national  and  local  codes  while  installing  PV  systems  and  Rapid 
Shutdown initiators. 
It is recommended that installers remove the terminal block from System Controller before 
wiring the jumpers/ cable headers. 
For systems with grid tied PV i.e., IQ6/7 or M215/250 microinverters, installers must wire a 
jumper across the NC3 and NC4 terminals. If using 28AWG to 16AWG wire, installers can 
simply jumper the RSD terminals as shown in the figure below: 
The RSD and other auxiliary contact terminals in the IQ System Controller 2 are rated for up 
to 16AWG wire. To avoid damaging the RSD terminals, installers MUST use the cable header 
assembly to connect wires thicker than 16AWG to the terminals, as shown in the figure below: 





