IQ7+ Micro Installation
Table Of Contents
- Important Safety Information
- The Enphase IQ System
- Planning for Microinverter Installation
- Parts and Tools Required
- Enphase Microinverter Installation
- Step 1: Position the Enphase Q Cable
- Step 2: Position the Junction Box
- Step 3: Mount the Microinverters
- Step 4: Create an Installation Map
- Step 5: Manage the Cabling
- Step 6: Connect the Microinverters
- Step 7: Terminate the Unused End of the Cable
- Step 8: Complete Installation of Junction Box
- Step 9: Connect the PV Modules
- Step 10: Energize the System
- Set Up and Activate Monitoring
- Troubleshooting
- Technical Data
IQ 7 / IQ 7+ / IQ 7X Micro Installation and Operation
© 2018 Enphase Energy Inc. All rights reserved. 141-00043-02
16
Step 3: Mount the Microinverters
A. If the Enphase DC bulkhead connectors are not already attached to the microinverters, attach
them now. Make sure they are fully seated.
B. Mount the microinverter bracket side up (as shown) and under the PV module, away
from rain and sun. Allow a minimum of 1.9 cm (3/4”) between the roof and the microinverter.
Also allow 1.3 cm (1/2”) between the back of the PV module and the top of the microinverter.
WARNING: Install the microinverter under the PV module to avoid direct exposure to
rain, UV and other harmful weather events. Do not mount the microinverter upside down.
C. Torque the microinverter fasteners as follows. Do not over torque.
• 6 mm (¼”) mounting hardware: 5 N m (45 to 50 in-lbs.)
• 8 mm (5/16”) mounting hardware: 9 N m (80 to 85 in-lbs.)
• When using UL 2703 mounting hardware, use the manufacturer’s recommended
torque value
AC Connector