The table below shows a timeline from system shutdown until the point when all loads are
powered back on. Note that this table assumes all loads can be successfully powered on
the rst try, post system restart. The sequence below will repeat if there are successive
failures. If any load causes up to ve system shutdowns that load will be skipped, and the 22
seconds delay associated with that load will also be skipped during the next system restart.
Consider a system with the following loads:
EVENT
TIME TAKEN (HOURS:
MINUTES: SECONDS)
TIME ELAPSED SINCE
SYSTEM SHUTDOWN
(HOURS: MINUTES: SECONDS)
System shutdown/Microgrid collapse N/A 00:00:00
System restart with highest priority loads powered on
• IQ8 Microinverters restart and provide
240V output
• Wi-Fi router + Modem is powered on
00:00:52 to 00:01:57 00:00:52 to 00:01:57
Refrigerator is powered on 00:00:22 00:01:14 to 00:02:19
Kitchen lights is powered on 00:00:22 00:01:36 to 00:02:41
Microwave is powered on 00:00:22 00:01:58 to 00:03:03