Using the Enphase Q Aggregator
The Enphase Q Aggregator lets you install systems up to 11.5 kW with only two line conductors and a
ground coming from the roof. It is usable in any position up to 45 degrees from horizontal. (NEMA 3R,
includes drain holes). The Q Aggregator bracket is ready to install on rail, but can be flipped for mount or
roof block.
You will need the following items:
Enphase Items
Enphase Q Aggregator(s) for multiple branch arrays
One bulkhead connector cap (Q-BA-CAP) (included with Q Aggregator). You may need to
order an extra cap if you connect only one branch circuit to the aggregator.
Enphase Q Aggregator Quick Install Guide.
Enphase Disconnect tool.
Other Items
Crimp tool PV-CZM-18100, -019100, or -22100 for Field Wireable connectors
Drill with an appropriately sized hole saw
Screwdrivers
Wire stripping tool
Torque wrench and sockets for mounting hardware
90° C-rated conductors for connections between the Q Aggregator and main PV breaker.