Installation RRU-N
Target Group
The target group for this instruction is personnel involved in the installation
of an RRU-N.
3.1 Preconditions
This section provides preconditions that must be met before starting the
installation work.
General Preconditions
Before starting site work, ensure the following has been implemented:
Site access permission received.
Ordered RRU-N, equipment, specified tools and other necessary facilities
have been delivered.
Site power is available.
Site grounding point is available.
Note: The terms earthing and grounding are synonymous.
Antenna system installed.
During outdoor installation, protection for the RBS is available in case of
bad weather.
Note: After installation, if the surrounding temperature changes between hot
and cold, then to avoid humidity damage the RRU-N must not be left
without power for more than 48 hours.
Equipment
The instructions in this document describe the installation, or use, of the
following hardware:
RRU-N
Front Sunshield
Mounting fixtures for mast and pole mounting (alternative)
Brackets for wall mounting (alternative)
Drilling template for wall mounting (when wall mounting alternative is used)
Grounding kit
Power cable
3
50/1531-LZA 701 0001 Uen PA4 2008-07-31