User's Manual

Installation RRU-N
3.2.1 Unpacking and Checking the Material
Unpack the RRU-N on-site. To avoid damage, the RRU-N should not be
unpacked elsewhere and then transported to site.
In order to avoid damage to the components due to electrostatic discharges
during unpacking, personnel must not come in contact with the connectors of
the RRU-N.
Ensure that the correct material has been delivered. If the material is damaged,
complain the supervisor or the transport company immediately.
3.2.2 Installing RRU-N on a Pole or a Mast
Warning!
Risk for falling objects, work at height in progress. Falling objects can cause
serious injury or even be fatal. Always wear a helmet and avoid standing in
the danger area.
Note: The following precautions must be taken when working at height:
Safety belt and safety helmet must be used.
Adequate protective clothing is essential in cold weather.
All lifting devices must be tested and approved.
A doctor's certificate for such work must be obtained.
To install the RRU-N on a pole or a mast, perform the following steps:
Note: Ensure that the threads on all stainless steel fixtures are treated with
anti-seize thread lubricant to minimize the risk of the nuts seizing.
5
50/1531-LZA 701 0001 Uen PA4 2008-07-31