7 Site Installation Tests
This section describes the test procedure for site installation tests.
7.1 Preconditions
Before starting the tests, ensure the following:
• A completed test record for Antenna System Tests is available
• The nominal AC mains voltage and/or DC supply on the site is known
Note: The information above can be found in:
Site Installation Documentation
• A test record is available
• Chapters Personal Health and Safety Information and System Safety
Information have been read
7.1.1 Documentation
The list below displays the manual required for site installation tests.
Table 25 Required M anual for Site Installation Tests
Product Name Description Product Number
OMT User’s Manual Included in OMT Kit EN/LZN 720 0001
7.1.2 Before Starting Test Procedure
Before starting the test procedure, ensure the following:
• All personal rings, wrist watches, and other metallic objects are removed
before working with the power system
• The necessary tools, instruments, and documentation are available
1
09
EN
/LZT 720 0027 Uen R8A 2006-06-27