RBS 2308 and RBS 2309 User’s Guide
7 Site Installation Tests
This section describes the test procedure for site installation tests.
7.1 Preconditions
Before starting the tests, ensure the following:
A completed test record for Antenna System Tests is available
The nominal AC mains voltage and/or DC supply on the site is known
Note: The information above can be found in:
Site Installation Documentation
A test record is available
Chapters Personal Health and Safety Information and System Safety
Information have been read
7.1.1 Documentation
The list below displays the manual required for site installation tests.
Table 25 Required M anual for Site Installation Tests
Product Name Description Product Number
OMT User’s Manual Included in OMT Kit EN/LZN 720 0001
7.1.2 Before Starting Test Procedure
Before starting the test procedure, ensure the following:
All personal rings, wrist watches, and other metallic objects are removed
before working with the power system
The necessary tools, instruments, and documentation are available
1
09
EN
/LZT 720 0027 Uen R8A 2006-06-27