User's Manual Part 2

RBS 2308 and RBS 2309 User’s Guide
Work Process for Antenna System Tests
This section describes the order in which to perform the tests. When the exit
criteria for each procedure are fulfilled, the tester enters the results in the test
record, then returns to the work process for the next s tep.
Naming a DTF Measurement
Checking the Installation
Calibrating the Antenna Tester
Performing DTF Tests
Performing SWR Test
Performing
Concluding Routines
Naming an
SWR Measurement
Calculating the
Feeder Attenuation
Calculating the
Feeder Delay
P010285B
Figure 36 Work Process for Antenna System Tests
The work order can be altered or tests can be removed due to local
circumstances. In this event, an investigation of the consequences must
be carried out. If the work order is changed or tests are removed, then the
department responsible for this manual must be notified and agree to changes,
or the responsibility is automatically transferred to the person making the
decision.
6.1 Checking the Installation
This section describes how to check that the antenna system installation is
correct.
8
9
EN
/LZT 720 0027 Uen R8A 2006-06-27