Installation Instructions

COMMISSIONING PROCEDURE 13 (23)
BRU1 MANUAL, Doc.no: b1commis Uen Rev PA5, 2004-02-20
8 Before Leaving the Site
1. Make sure all plugs and connectors are connected.
2. Set the virtual thumb wheel to position zero “0” for normal node
execution.
3. Check that all outstanding items are listed in the Commissioning Test
Record, and also, that the person and company responsible for the item/-s,
is informed.
When the hardware commissioning procedure is completed, please
proceed with the software part of the Commissioning Procedure.