Installation Guide

3. Make sure frame is level.
Screw the frame to the opening.
4. Cover hole with plastic cap.
2. Drill 7/16 hole into first layer of
Side frames for cap and ¼” hole on
the other layers.
Side needs 4-5 Screws ( 6” from bottom ,
6” from top and other screws spaced
equally along the frame).
Top track needs 2-3 screws spaced
equally along the top piece.
Frame Installation
1. Apply the Liquid Nail under the track and place the frame in the
opening.
Only Liquid Nail is recommended for bottom track for better waterproofing unless floor is
not level and you will need to anchor the track to the floor.