Technical data
Flow Meter FC01-Ex Flow Meter FC01-Ex
8 Ex atmosphere - Definitions and mounting instructions 8 Ex atmosphere - Definitions and mounting instructions
2.6.1.2.1 Liquid media
● In the case of vertical pipelines the monitoring head should be installed where the flow is
rising, if possible.
● For horizontal pipelines the monitoring head should be mounted on the underside of the
line (suspended).
● The monitoring head should be installed only in a straight section of piping. There should
be a distance of at least 20 pipe diameters before the monitoring head, and 5 pipe diam-
eters after the monitoring head before or after bends and changes in pipe diameter, to
avoid any effects of turbulence (fig. 3).
● Flow past the sensor should be from the side marked with a green dot.
2.6.1.2.2 Gases
If gases are to be monitored, the mounting attitude of the monitoring head is unimportant in either
vertical or horizontal pipelines. There should be a distance of at least 20 pipe diameters before the
monitoring head, and 5 pipe diameters after the monitoring head before or after bends and
changes in pipe diameter, to avoid any effects of turbulence (fig. 3).
2.6.1.2.1 Liquid media
● In the case of vertical pipelines the monitoring head should be installed where the flow is
rising, if possible.
● For horizontal pipelines the monitoring head should be mounted on the underside of the
line (suspended).
● The monitoring head should be installed only in a straight section of piping. There should
be a distance of at least 20 pipe diameters before the monitoring head, and 5 pipe diam-
eters after the monitoring head before or after bends and changes in pipe diameter, to
avoid any effects of turbulence (fig. 3).
● Flow past the sensor should be from the side marked with a green dot.
2.6.1.2.2 Gases
If gases are to be monitored, the mounting attitude of the monitoring head is unimportant in either
vertical or horizontal pipelines. There should be a distance of at least 20 pipe diameters before the
monitoring head, and 5 pipe diameters after the monitoring head before or after bends and
changes in pipe diameter, to avoid any effects of turbulence (fig. 3).
D = nominal pipe diameter
D = nominal pipe diameter
D
20 x D 5 x D
5 x D
D
20 x D
fig. 3
D = nominal pipe diameter
D = nominal pipe diameter
D
20 x D 5 x D
5 x D
D
20 x D
fig. 3