Instructions / Assembly

T: Terminal Posts
L: Line Posts
Property Line
Property Line
Property Line
HOUSE
String over property line
L
T
T
T
T
Stakes
Stakes
T T
T
L
L
L
L L L L
Drive GateWalk Gate
4"
4"
String Line
Tap Post
Down
Raise
Post Up
Te rminal
Post
Te rminal
Post
Line Post Line Post Line Post
Brace Band
Tension Bands
End & Gate
Post
Corner
Post
Rail End
Eye Top
Swedge End Top Rail
Brace
Band
Post Cap
Terminal
Post (end)
Tension Band
Top Rail Sleeve
ADDING OR
SPLICING FABRIC
From an end of the fabric,
remove a strand of wire. Join
the two sections together
and wind the removed wire
down through the ends, in a
corkscrew manner. Note: a
second strand of wire may
have to be removed in order
to mesh properly.
REMOVING FABRIC
With pliers, open the top and
bottom ends of wire where
you wish to terminate or
remove fabric. Unwind the
strand and twist through the
links until the wire comes out
of the fabric, in a corkscrew
manner.
Tie Wires
Gate
Latch
Post
Hinge
Frame
Hinge
Gate Opening
Line Post
Terminal Post
(corner)
(Insert 1 rail end)
Fence
Strecher
Tension Bar
8"
18" to 30"
18" to 24"
6"
Terminal Post
Hole
Ground
Line Post
Hole
Te rminal
Post
Line Post
Crayon
Marks
10’ Max.
Terminal
Post
Line
Post
Ground
Crown
Learn more at
homedepot.com
¢
1
Locate Terminal Posts and Install
(Corner, End and Gate Posts)
¢
2
Locate Line Posts and Install
¢
3
Install Fittings to Terminal Posts
Before You Start Digging...
IMPORTANT
Determine the boundary lines of the property, insert stakes and stretch string around all
stakes. Mark locations for all terminal posts (corner, end and gate) and make sure they are
4” inside property boundaries. Mark location for each gate post with a stake. Gates come
in standard opening widths of: Single Walk - 36”, 39”, 42” and 48”; Double Drive - 10’ and
12’. (i.e. if gate opening is 42”, gate post spacing should be exactly 42”, measured between
inside post surfaces. If opening is 48”, spacing should be exactly 48”. See Step 6). Dig all
terminal post holes (refer to diagram below for width and depth).
Mark the ground line on all posts for correct height of fence. The height of the terminal
posts, above ground, will equal the height of the chain link fabric plus 2”. The height of the
line posts will equal the height of the fabric less 2”. Set
terminal posts in fast setting concrete in center of hole
keeping ground line at ground level. Use a level to check
plumb. Crown all post footings so water drains away
from posts.
1. Check with local utility company for cables, underground lines, etc.
2. Check local codes regarding height, locations, etc. A permit may be necessary.
3. Consult plat of survey or professional surveyor to ensure that your fence footings
are located within your property lines.
(NOTE: Use
approximately
one 50 lb. bag
of fast setting
concrete for
each line post
hole, and two 50
lb. bags of fast
setting concrete
for each terminal
post.)
After the concrete has hardened, stretch a string (positioned on the outside post face)
between terminal posts. The string should be 4” below the top of the post (see diagram
below). Measure the distance between the terminal posts and refer to the Terminal/Line Post
Spacing Chart on reverse side for positioning of line posts. With stakes, mark the locations
of all line posts and align with the centers of the terminal posts.
Dig all holes for line posts (refer
to diagram above for width
and depth) and set posts in
concrete.
After concrete has hardened
enough for posts to remain
plumb, adjust all line posts to
be even height with the string
by gently moving posts up or
down in the footings. (Use a
carpenter’s level for accuracy).
The outside faces of the line
posts should be 1/4” inside the
string line.
Review the Material Check List on reverse side for descriptions and
number of fittings required.
After concrete footings have hardened, slip the tension bands over
terminal posts making sure they are evenly spaced. The long, flat
surface should face the outside of the fence. Carefully add brace
bands making sure not to bend or distort. Bolt heads should be
on the outside of the fence and threaded ends inside. Fit all post
caps.
¢
4
Install Top Rails
Place an eye top fitting on the end of each line post. Flat side
should be toward outside of the fence. Insert one length of top
rail pipe through an eye top nearest a terminal post. Insert a
rail end on the top rail and attach to terminal post with a brace
band. Fasten with a 5/16” x 1-1/4” carriage bolt. Continue to
join lengths of top rail by forcing swedged (or crimped) ends of
top rail together through eye tops. (If joining non-swedged top
rail sections, sleeves can be used as pictured below). When next
terminal post is reached, measure and cut the top rail to fit tightly between the last length
of top rail and the rail end fastened to the brace band on the terminal post. Fasten with a
carriage bolt.
¢
5
Affix and Stretch Chain Link Fabric
Beginning at a terminal post, lay the chain link fabric on the ground and unroll to next terminal
post. Unroll enough fabric to cover the opening between the terminal posts. (See figure below
for adding and removing fabric). Insert a tension bar through the end of the fabric and attach
to tension bands which were previously placed on the terminal posts. Fasten (not too tightly)
with 5/16” x 1-1/4” carriage bolts - heads on the outside of the fence and threaded ends inside.
Stand the entire
fence section
upright, leaning
against the
framework.
Loosely attach
fabric to top rail
with tie wires to
hold in place.
From the terminal post, which
already has fabric attached, stretch
the fabric to the opposite terminal
post (see diagram at right). Insert
a tension bar 4 feet inside the open
end of the fabric. Fasten one end
of the fence stretcher to the tension
bar or stretcher bar and the other
end to the terminal post. Stretch
the fabric until there is a slight
tension when squeezed by hand.
Either add or remove fabric for
exact length. Insert a tension bar
at end and connect to the tension
bands on the terminal post.
Remove fence stretcher and secure
fabric to top rail with tie wires. Spacing
should be 24” apart on top rail and 12”
apart on line posts. Securely tighten
nuts on all brace and tension bands.
NOTE: Clearance for hinges and latches (4” for
walk gates and 6” for drive gates) is included in
stated gate opening width.
¢
6
Hang Gates
Attach frame hinges to gate frame. Install post
hinges to gate post. Install top post hinge
with pin pointing down and bottom post hinge
with pin pointing up. This will prevent the gate
from being lifted off the hinges. Place gate in
position by aligning the top of the gate with the
top of the fence and adjust the hinges to allow
for a full swing. Install gate latch at desired
height that’s suitable to your usage and fasten
all bolts.
Follow the same directions to install Drive Gates.
INSTALLATION INSTRUCTIONS
CHAIN LINK FENCE