STEP NINE Exteria J-channels may be used for inside corner treatments. Panels may be scribed and
cut to fit into the corner (Figures #9 & 10). It is recommended to sleeve the corner with vinyl or
aluminum coil prior to installation of panels. Caulk corner after installation.
Figure 9 Figure 10
STEP TEN When completing a wall, face nailing may be necessary. If face nailing is employed, pre-drill
a hole in an inconspicuous area, such as a mortar joint. The hole must be larger than the shank of the
nail or screw, but smaller than the head, to allow for possible expansion. The head can be covered with
matching paint.
CREEK LEDGESTONE INDIVIDUAL MOLDED CORNER INSTALLATION
The siding must be installed on adjacent walls PRIOR to installing corners.
STEP ONE Be sure the starter clip is affixed at the bottom of the wall’s corner placed on top of the
starter strip. Slide your first Creek Ledgestone molded corner over the siding and engage it into the
starter clip. The corner offers two (2) pairs of fastening positions to choose from. For fasteners,
galvanized screws are recommended. Once positioned properly, insert one (1) fastener on each side
(Figure #11).
Figure 11
STEP TWO Take the next corner and engage it into the corner below. Some adjustment may need to
be made at the vertical overlap of two (2) corners (as they are installed) in order to maintain the corner/
panel horizontal alignment. There is approximately a 1/2” vertical adjustment available. Gently tug the
bottom of the corner to ensure it is properly engaged. Repeat this step until the corner installation is
WI-QPC-1019REV- Page | 6 of 7 CREEK LEDGESTONE