ASSEMB LY I NST RUCT I ONS FOR FM256, FM257
IMPORTANT
TURN OFF THE POWER AT THE MAIN FUSE
OR CIRCUIT BREAKER BOX
BEFORE STARTING INSTALLATION
Carefully unpack and identify all parts before assembly.
Bulb not included.
1. Install glass panels:
A. Take one glass panel and carefully slip through
inside of main frame. Position it so both side edges 
of the panel are located hidden behind vertical ribs 
of the main frame.
B. Lock the glass panel by bending tabs located at 
top and bottom of main frame.
C. Repeat other glass panels.
2.  Attach mounting bar securely to ceiling junction box 
with two machine screws (supplied with junction 
box) through slot at each end of mounting bar.
Note: mounting bar should be installed with "GND" 
imprint and/or two dimples facing down.
3.  Fasten one hex nut about 3/4" (19 mm) down from 
one end of threaded pipe. Then screw same end of 
threaded pipe into center hole in mounting bar. At 
this point test install the main frame onto ceiling 
through this threaded pipe and make certain 3/8"
(10 mm) of pipe protrude below. If not, then adjust 
the threaded pipe location by screwing up or down 
accordingly. Once correct threaded pipe location has 
been adjusted, remove main frame and tighten hex 
nut against mounting bar. Make certain not to spin 
threaded pipe during tightening.
4.  Spread the electrical wires so that the black 
wires are on one side of the outlet box and 
the white wires are on the other side.
5.  Electrical connections:
Connect the white wire from the fixture to the white 
wire of the outlet box. Connect the black wire from 
the fixture to the black wire of the outlet box.
NOTE: Black outlet box wire may be red, round & 
smooth and/or have copper conductor. White outlet 
box wire may be square & ridged and/or have a 
silver conductor.
6.  Grounding Connection:
Connect fixture ground wire (without insulation) to 
ground wire from outlet box (usually with green 
insulation) with wire connector (not provided).
IMPORTANT: Never connect ground wire to black 
or white power supply wires.
7.  While making certain all electrical wires are tucked 
inside of main frame, install the main frame by 
fastening with a lock washer and coupler onto the top
threaded pipe.
8.  Install bulb (not included). See relamping label 
located at socket area for type and maximum
allowed wattage.
9.  Install the center pipe by screwing onto bottom of 
main frame. Note correct position of center pipe
at illustration.
10.  Install glass plate by slipping through the already 
installed center pipe and then fastening with a finial. 
IMPORTANT: Do not over tighten.
MUR R AY FEI SS
©M UR R AY FE I SS I M PORT LLC .
A Quality Home Brands Compan
Outlet Box
Hex Nut
Outlet Box
Mounting Screw
(not supplied)
Mounting
Bar
Supply
Ground Wire
Supply
Wires
Fixture
Wires
Fixture
Ground Wires
Finial
Socket
Main
Frame
Glass Panel
Center Pipe
Glass Plate
Lock Washer
Coupler
1
2
3
4
5
7
8
9
10
Bulb
(not included)