4.1.2 Steps for commissioning the SPC200 as a field bus slave
The following steps are required for commissioning the
SPC200 as a field bus slave:
1. Set the following when configuring the field bus module:
Settings
Description
PROFIBUS address Permitted address range: 0...125
1)
1)
In some cases is limited by the DP master used
Modification by a DP master is not possible.
2. Install GSD file and symbol file.
3. Configure the PROFIBUS with the appropriate configur
ation software (e.g. with STEP 7 hardware configurator).
4. Test the field bus connection in online mode.