Instructions for installing Fiberbloxx product
Supplies included
*Steel post (2) *Anchor bolts (3)
*Bolts (3) *Nuts (3)
*Washers (3) *Steel cables (2)
*Flat steel (24”x1.5”) (1 for curved walls 2 for straight walls)
Supplies not included
*Pencil *Tape measure
*Pea gravel *Motorized compactor
*Hand tamper *Level
*Drill bit *Drill
*Hammer *Shovel
*Wrench *Ratchet/socket
Step 1
Find on your basement where you want the top of your wall to be. With a pencil mark that
spot. Measure down 37.5 from that mark (31.5” for the wall and 6” for the pea gravel). Set
your section of wall there so you know that you are digging your trench correctly. Ideally the
perfect sized trench would be 6' long x 12” wide x 6” deep. Its better to have the trench a
little larger than the product. Now measure down 31.5” from your mark and put another
mark on the wall. Fill the trench with 6” of pea gravel rock. Compact the pea gravel with a
tamper (not included) to make a firm base to set the wall on. Take a level and make sure the
base is level and ready for the wall.
Step 2
Set the wall tight against the foundation making sure it is level. Once you have it in place,
drill with a 1/4” concrete bit (not included) thru the top pre-drilled hole in the wall. Drill
approximately 2” into the concrete wall. Line up the pre-drilled steel with the all three holes
that are in the wall. Screw anchor bolt into the wall until it is tight. Repeat this process for
the next two holes.