Installation Guide

Step 4: Insert bolts with washers.
Place the post into position over the drilled holes and insert a 1/4 in. x 3 in.
concrete bolt with small 5/16 in. washer into each of the four holes (Figure 3).
Step 5: Loosely tighten post baseplate.
To allow rail and / or stair installation, loosely tighten the bolts, leaving the bolt
heads approximately 1 in. above the baseplate (Figure 4).
Step 6: Attach post baseplate cover.
Aer the rails and / or stairs have been installed, plumb and tighten the posts.
Position both halves of the baseplate cover on either side of the post above the
baseplate and below the bottom rail. Align the locking pins on one half to the
matching holes on the other half and slide together.
Optional: Apply PVC adhesive to the locking pins prior to sliding halves
together for a secure fit (Figure 5).