Owner's manual

Document #51131 Rev. B 5/10/02 P/N 51131:B 1 of 2
The communicator cabinet may be either semi-flush or
surface mounted. The door is removable during the installa-
tion period by opening and lifting off the hinges. The
cabinet mounts using two key slots and two additional 0.25"
diameter holes located in the backbox. The keyslots are
located at the top of the backbox and the two securing holes
at the bottom.
Carefully unpack the system and check for shipping damage. Mount the cabinet in a clean, dry, vibration-free
area where extreme temperatures are not encountered. The area should be readily accessible with sufficient room
to easily install and maintain the panel. Locate the top of the cabinet approximately five feet above the floor with
the hinge mounting on the left. Determine the number of conductors required for the devices to be installed.
Sufficient knockouts are provided for wiring convenience. Select the appropriate knockout(s) and pull the
required conductors into the box. Note that there are no knockouts on the left (hinged) side of the cabinet. All
wiring should be in accordance with the National and/or Local codes for fire alarm systems.
Backbox Mounting
Open the door and lift the door off the pin hinges
Mark and predrill holes for the top two keyhole mount-
ing bolts using the dimensions shown in Figure 2
Install two upper fasteners in the wall with the screw
heads protruding
Using the upper 'keyholes', temporarily mount the
backbox over the two screws
Mark the lower two holes, remove the backbox from
the wall and drill the lower two holes in the wall
Before mounting the backbox to the wall, install the
supplied transformer in the backbox by sliding the bot-
tom transformer flange into the lower transformer
mounting slot. Position the hole in the top transformer
flange over the transformer mounting stud. Refer to
Figure 1 for the location of the slot and stud
Secure the transformer with the supplied nut and
attached washer
Mount the backbox to the keyhole mounting bolts,
install and tighten the remaining fasteners
Main Circuit Board Mounting
When the location is clean and free of construction dust or other potential contaminants, install the main PC
board by installing the four supplied standoffs on the four main circuit board mounting studs located in the
backbox. Refer to Figure 2
Position the main circuit board’s four corner mounting holes over the four standoffs just installed. Be certain
to observe the proper ESD (Electro Static Discharge) precautions to prevent damage to the static sensitive
circuits. This includes, but is not limited to, use of a wrist strap
Secure the main circuit board to the standoffs with the four supplied screws and attached washers
Plug the transformer connector into the main circuit board connector J4. The connector is keyed and can only
be plugged-in one way.
When wiring is completed, install the door on the backbox pin hinges and the window bezel in the door
Transformer
flange
Transformer
mounting slot
Transformer
mounting stud
Top of backbox
411XFRMT.CDR
Ground
Stud
Figure 1: Transformer Mounting
Document #51131 Rev. B 05/10/02 ECN 02-255