- Issue Date: 08- 04- 2003
- Overview
- Verifying the Site Preparation
- 2.1. Site Preparation Checklist •24 Indoor BaseStation
- 2.2. Preparing the Floor
- Installing the Cabinet
- Connecting the Power System
- 4.1. Routing the Cables
- 4.2. Connecting to Power and Ground
- Connecting the Core Network Cables
- Connecting the Antennas Cables
- Installing the Alarm Connections
- Powering Up the Cabinet
- Powering Down the Cabinet
- Verifying the Installation
- 10.1. Verifying the Physical Installation
- 10.2. Verifying the Base Station Operation
- RadioRouter BaseStation Site Preparation Punchlist
- RadioRouter BaseStation Installation Punchlist
- tables
Page 9
Procedure 3-2 Lifting the Cabinet
Once the cabinet is near its final position, it can be moved into place. It is recommended that the
cabinet be lifted by a hoist or crane using heavy duty structural straps with 1000 lb load capability.
Note:
Before lifting the cabinet into place, make sure all necessary holes have been drilled. See Section
2.2. Prepar ing the Floor. Make sure the back panel and front door have been removed.
1.
Remove the 1U blank panel at the top of the cabinet.
Figure 3.3 Top of Cabinet with Panels Removed
2.
Route the structural straps through the top of the cabinet from front to back.
3.
Lift the cabinet into place.
4.
Replace the 1U blank panel at the top of the cabinet.
RadioRouter
®
BaseStation Installation Guide — Draft
Version 0.5 - © 2003
Page 9