User's Manual
Table Of Contents
- toc
- Issue Date: 08- 04- 2003
- Overview
- Verifying the Site Preparation
- 2.1. Site Preparation Checklist •24 Indoor BaseStation
- 2.2. Preparing the Floor
- Installing the Cabinet
- Connecting the Power System
- 4.1. Routing the Cables
- 4.2. Connecting to Power and Ground
- Connecting the Core Network Cables
- Connecting the Antennas Cables
- Installing the Alarm Connections
- Powering Up the Cabinet
- Powering Down the Cabinet
- Verifying the Installation
- 10.1. Verifying the Physical Installation
- 10.2. Verifying the Base Station Operation
- RadioRouter BaseStation Site Preparation Punchlist
- RadioRouter BaseStation Installation Punchlist
- tables
Page 18
Procedure 4-2 Connecting the Power Cables
WARNING:
WHEN PERFORMING ANY TASKS INVOLVING THE POWER SYSTEMS,
MAKE SURE THAT THE POW ER IS NOT LIVE. ALL P OWER OPERATIONS
SHOULD BE PERFORMED BY QUALIFIED PERSONNEL ONLY.
1.
Locate the DC power connection point and the DC return connection point. See Figure
4.7 Power Connections Viewed from inside the Cabinet and Figure 4.8 Schematic View of
Power Connections.
2.
Connect the power cable to the connectors with 6 AWG wire with a 2–hole lug for a 1/4”
diameter stud.
3.
Fasten the lug on to the stud with the nuts provided. Tighten nuts to 40–50 in-lb torque.
4.
Connect the other end of the cable to the DC power source.