Installation Instructions

SuperFast
®
Hurricane!
!
Installation Instructions for SuperFast® Hurricane
I. Before You Start / Preparations
Please read all the instructions before you begin the installation.
Improper installation will void warranty.
Important
All wood based products, even those specifically designed to have increased resistance to moisture,
are hydroscopic (they will react to the moisture in the environment) and as a result will expand or
contract accordingly. All sources of under floor moisture must be rectified prior to the installation of the
floor. Any construction dampness must be completely dry. Although this product has been designed
with bathroom installation in mind it is not waterproof and excessive wetting is to be avoided and
water spillages dried immediately. At no time should standing water be left on the floor. It is important
that you check each plank for any manufacturing defects. Do not install. Return the product or contact
the manufacturer at (404) 794-3688.
Calculate the room surface prior to installation and plan an extra 10% of flooring for waste.
Keep the boards in room temperature for at least 48 hours in unopened package before you
start the installation. The room temperature must be between 18° and 25 °C (65-78 °F) before
and during installation. For floor surfaces exceeding 400m (4350 ft )and or lengths exceeding
20m (66 ft ) and overlaps to new rooms and floor surface which do not join symmetrically, use
expansion joints to divide the floor sections.
Inspect your subfloor before you begin. It must be clean, dry (max. 2.5% moisture content -
CM method) and level to 5mm (3/16”) within a 3 meters (10 foot) span.
If this flooring is intended to be installed over an existing wooden floor, it is recommended to
repair any loose boards or squeaks before you begin installation.
With a floating floor you must always ensure you leave a 1cm (1/2”) gap between walls and
fixtures such as pipes and pillars, stairs, etc. Tip: When installing around pipes, drill the holes
20 mm (3/4”) larger than the diameter of the pipes.
It is required to install a moisture barrier. Underlayments thicker than 1/8” are not advised.
(Note: some collections may have a pad factory pre-attached to the back of planks, so no
additional pad is needed.) If the laminate flooring is being installed over concrete subfloors, a
minimum 0.15mm (6 mil) plastic poly sheeting should be used as a moisture barrier.
Relative Humidity Levels of your room should be maintained at 40-65 % at 18-24 °C (65° -
75°F).

Summary of content (6 pages)