This integration guide will help set up the charge/discharge parameters of Fortress Power batteries and
commission them as they relate to Sol-Ark inverters.
Tech-Support Contact Information
· Phone: (877) 497-6937 ext. 2
· Support Tickets: https://www.fortresspower.com/support/
Useful Links
· Warranty Submittal: https://www.fortresspower.com/warranty/
Share Sol-Ark Monitoring w/Fortress
Set up Wi-Fi with Sol-Ark Inverter using Sol-Ark’s PowerView App (search for Powerview in the app store, but it is called
PV Pro) and have your site name and Wi-Fi dongle serial number handy to register the system online with Sol-Ark.
After registering, use a laptop to log into Powerview via a web browser at http://pv.inteless.com/
Next, share the plant including manager level permissions with techsupport@fortresspower.com
Unpack Batteries + Check Voltage
1. Unpack the batteries and turn each battery on by itself.
2. Note the voltage of each battery and serial number. The serial numbers are useful during warranty submittal.
3. The batteries must be within +/-0.5V of each other before commissioning. Groups of 4 batteries or more may
require a narrower voltage range to commission properly.
4. Turn off the batteries and install them in parallel.