Victron Integration Guide

Rev 2.1 09-14-21
1
Fortress Power - Victron Inverter Guide
Introduction
Battery Datasheets / Manuals: See “Downloads” section of individual product pages
Email: techsupport@fortresspower.com
Discord Support: https://discord.gg/kxX6QMjKFw
Phone: (877) 497-6937 x 2
Hours: 9:00AM - 6:00PM EST Use Discord for After Hours / Weekends
Warranty Submittal: https://www.fortresspower.com/warranty/
Join Our Discord Chat
Step 1 Getting Started. Turn each battery on individually while unpacking the batteries and note the voltage
of each battery as well as the serial numbers. The batteries must be within +/- 0.5V of each other before
commissioning. Turn off the batteries and install in parallel. Install the battery-to-battery communication cables and
proceed with system commissioning.
Pro tip: If the battery voltages are significantly different, wire the batteries in parallel without communication cables
and only turn on the lowest voltage battery. Use the inverter or external charger to charge the battery to the
voltage of the 2
nd
lowest battery. Turn the 2
nd
battery on and charge the battery bank to the 3
rd
lowest battery
voltage. Repeat until all batteries are at the same voltage. Keep total charging voltages under 15A per battery during
this process.
Pro tip: If the batteries are just slightly outside the +/- 0.5V range, you can avoid using an inverter or an external
charger to balance the batteries by only turning the lowest voltage batteries on (ONLY if within 0.5V relative to each
other) and allowing those batteries to balance. Repeat this process with the highest voltage batteries. This brings
the lowest and highest voltage battery towards to the middle of the group.
Pro tip: It is not usually necessary to apply a firmware update to Fortress batteries during system commissioning,
but our installer firmware update tool can help speed up commissioning times.
Step 2 Setup the Victron Hardware. Victron monitoring is supported with a variety of accessories. For
closed loop operation the VE.CAN protocol needs to be implemented. This is supported with the Cerbo GX, CCGX,
VenusGX, Octo GX, CANVU GX communication centers. It is recommended prior to commissioning the batteries
you use VictronConnect to get the latest release of firmware loaded.
Power up the Victron Inverter from grid, generator, or batteries. This
step can be done during pre-commissioning while running the
batteries in “master only” mode (all batteries need to be within 0.5V),
ahead of installing the battery communication circuits. Set up Victron Quatro
Inverter using the VE Configure App or using the touchpad and buttons.