Manual

920-087-02(9-03)
AppendixB: ElectricalWiringfor 265 VoltModels
NOTE: It is recommended that the PXSB subbase assembly, the PXCJ conduit kit and the PXDS disconnect switch be installed on all
hardwired units. If installing a flush-floor mounted unit, make provisions for allthe linevoltage power leads and conduit to be removed for
ease of maintenance and service to the chassis.
Toinstall the linevoltage power leads and conduit to the chassis, follow the instructions below.
1. Remove the four control box retaining screws (A) and open
the control box.
2. Punthe chassis power lead wires (B) (locatedon the bottom-
right side of the control box) through the plastic bushing so
they are located inside the control box.
3. Remove the plastic bushing.
4. Route the line voltage power leads through the hole where
the plastic bushing was located, and secure itsconduit (use a
1/2" straightconduit connector,with the Iocknut on the inside
of the control box.)
5. Makethe appropriate electrical connections within the control
box,then secure the box onthe chassis. Detailed instructions
are included with the installation instructions for the conduit
kit (PXCJ).
6. Route the line voltage power conduit from the control
box straight down the right front to the bottom side of the
chassis. This will allow the front cover to be installedwithout
interference with the electrical conduit.
Figure 11
LineVoltageConnections
Fuse holder
SCOWS
Inside back of co_rol
panelcove_
19