Installation Guide

1100 S. Huron Road, Green Bay, WI 54311
4Ever Composite Door Frame Installation Instructions
Installation Instructions - 4Ever Composite Frame 4/21/2016
Contents:
1. 83 in. left side frame with weather seal
2. 83 in. right side frame with weather seal
3. 36 in. top frame with weather seal
Other Components Required:
1. 4Ever Composite Brickmould kit
2. Interior casing kit
3. Shims
4. (6) #8 x 1-5/8 in. screws to fasten frame
together
5. (10) #10 x 3 in. screws to fasten frame to
rough opening
Tools Required:
1. Tape measure
2. Safety glasses
3. Power drill/driver
4. Power chop saw or miter box
5. Framing square
6. Level
Installation Instructions:
1. Measure the rough opening.
2. Trim the frame to fit around the door slab being
used (about 1/8 in. gap) and also to fit in the
rough opening (about 1/2 in. gap.) The thick part
on the bottom of the side frame is factory cut at 5
degrees to fit most sills. The top of the side is
notched to fit the top frame. Trim the bottoms to
fit the sill being used and to fit the height. Cut the
top frame 1-1/2 in. smaller than the final frame
width needed.
3. Screw each side frame to the top frame with (3)
#8 x 1-5/8 in. screws.
4. Set the frame assembly in the rough opening.
Shim the frame in place at 5 locations on each
side. Ensure it is plumb, level and square.
5. Fasten the frame to the rough opening with #10 x
3 in. screws through the side frames at each shim
location underneath the weather seal.
6. Install the 4Ever Composite Brickmould kit on the exterior of the door frame.
7. Install interior trim on the interior of the door frame.
8. Install hinges and lock plates as needed for the door being hung on the frame. Route the frame to fit the hinges and
lock plates selected.
9. For primed and woodgrain composite jambs, finish the surface of the frames within 15 days of installation to
prevent the factory primer from breaking down. Woodgrain has a tan primer on it to accept stain, clear coat, or
paint.
10. Seal with high quality caulk: inside top corners, bottom corners to sill, brickmould to siding, and brickmould to
frame.