Owner's manual

© The Fulton Companies 2014
INTRODUCTION HPN-IOM-2014-0416 SECTION 3
1-2
Overview
Prior to shipment, the following inspections and tests are
made to ensure the highest standards of manufacturing for
our customers:
Material inspections
Manufacturing process inspections
American Society of Mechanical Engineers (ASME)
welding inspection
ASME hydrostatic test inspection
Electrical components inspection
Operating test
Final engineering inspection
Crating inspection
This manual is provided as a guide to the correct operation
and maintenance of your Fulton equipment, and should be
read in its entirety and be made permanently available to the
sta responsible for the operation of the heater. It should not,
however, be considered as a complete code of practice, nor
should it replace existing codes or standards which may be
applicable. Fulton reserves the right to change any part of
this installation, operation and maintenance manual.
Installation, start-up, and maintenance of this equipment
can be hazardous and requires trained, quali ed
installersand service personnel. In order to meet Fulton
warranty requirements, this unit must be commissioned
by a Fulton Factory Technician. Trained personnel are
responsible for the operation and maintenance of this
product, and for the safety assurance of operation and
maintenance processes.
Do not install, operate, service or repair any component
of this equipment unless you are quali ed and fully
understand all requirements and procedures.
When working on this equipment, observe all warnings,
cautions, and notes in literature, on stickers and labels, and
any additional safety precautions that apply. Follow all safety
codes and wear appropriate safety protection. Follow all
jurisdictional codes and consult any jursidictional authorities
prior to installation.
Warnings & Cautions
WARNINGS and CAUTIONS appear in various chapters of this
manual. It is critical that all personnel read and adhere to all
information contained in WARNINGS and CAUTIONS.
WARNINGS must be observed to prevent serious injury
or death to personnel.
CAUTIONS must be observed to prevent damage
or destruction of equipment or loss of operating
e ectiveness.
All Warnings and Cautions are for reference and guidance
purposes, and do not substitute for required professional
training, conduct, and strict adherence to applicable
jurisdictional/professional codes or regulations.
Disclaimers and Local Codes
Installation of the equipment shall conform to all the
requirements or all national, state and local codes established
by the authorities having jurisdiction or, in the absence
of such requirements, in the US to the National Fuel Gas
Code ANSI Z223.1/NFPA 54 latest edition, and the speci c
instructions in this manual. Authorities having jurisdiction
should be consulted prior to installation.
The boiler heat exchanger is manufactured and stamped
in accordance with ASME Boiler and Pressure Vessel Code,
Section I or Section VIII, Div. 1.