Step Action
5.
Plug in Circuit Breaker:
6.
Mark the label to the left of the circuit breaker according to standard practice in your network.
7.
Feed a wire pair from the top of the bay down to the desired location.
8.
Locate and dress the pair to tie bars in the right back corner of the DC wiring area:
9.
Terminate the send on the circuit breaker lug landing using the hardware provided.
10.
Terminate the return on the return bus located on the back wall of the distribution area using the
hardware provided.
11.
Torque all fasteners to 65 inĀ·lbs (7 Nm) using an insulated extension at least 5 inches long.
Secure DC Pairs Securely
to Tie Bars