Product Manual
Table Of Contents
- Vivid™ E80 / Vivid™ E90 / Vivid™ E95
- Table of Contents
- Chapter 1
- Introduction
- Chapter 2
- Site Preparations
- General Ultrasound system requirements
- Facility needs
- Environmental Dangers
- Chapter 3
- System Setup
- Setup reminders
- Receiving and unpacking the equipment
- Packing materials - recycling information
- Preparing for setup
- Completing the setup
- Configuration
- Connectivity overview
- Connectivity setup
- Product Locator Installation Card
- Chapter 4
- General Procedures and Functional Checks
- Chapter 5
- Components and Functions (Theory)
- Software overview
- InSite ExC
- Vivid E80/E90/E95 overview
- Top Console with LCD monitor and Operating Panel
- Main Console
- Air Flow control
- Casters and brakes
- Front End Processor (FEP)
- Back End Processor (BEP)
- Power distribution
- Input and Output (I/O) modules
- Restart Vivid E80/E90/E95 after diagnostics
- Chapter 6
- Service Adjustments
- Chapter 7
- Diagnostics/Troubleshooting
- Chapter 8
- Replacement Procedures
- Warnings and important information
- Loading the software
- Replacing covers and bumpers
- LCD Monitor and LCD Arm parts replacement
- Upper OP Panel/Touch Panel Assembly replacement
- Lower Operating Panel Parts replacement
- A/N Keyboard parts replacement
- Other Top Console Parts replacement
- Replacing XYZ Parts
- Main Console parts replacement
- Casters and Brakes replacement
- Front End Processor (FEP) / Card Cage parts replacement
- Back End Processor (BEP) parts replacement
- Main Power Supply replacement
- Patient I/O assembly replacement
- Peripherals replacement
- Cables replacement
- Chapter 9
- Renewal Parts
- List of Abbreviations
- Software for Vivid E80/E90/E95
- Covers and Bumpers
- Top Console parts
- XYZ parts
- Main Console parts
- Casters (wheels) parts
- Front End Processor (FEP) Card Rack parts
- Back End Processor (BEP) parts
- Main Power Supply
- I/O modules parts
- Peripherals for use with Vivid E80/ E90/E95
- Mains power cables - Vivid E80/E90/ E95
- Internal Cables - Vivid E80/E90/E95
- ECG cables - Vivid E80/E90/E95
- Physio TX parts
- Probes for Vivid E80/E90/E95
- Options - Vivid E80/E90/E95
- Chapter 10
- Care and Maintenance
- Index
Replacement Procedures
8-50 Vivid E80/E90/E95 – Service Manual
GC091052
Rev. 3
Install the Wagon, A/N Drawer Sheet Met.
Follow these steps to install the Wagon, A/N Drawer Sheet Met.
1. Fasten the ground cable (Cable, GND, A/N Drawer) to the
Wagon, A/N Drawer Sheet Met. Assy by use of screw M4x6
/ washer tooth 4.3 (both sides of cable shoe), torque:
5,7 Nm.
2. Slide the Wagon, A/N Drawer Sheet Met. Assy into the
J-Rails w/Linings.
3. Place the J-Rails / Wagon into the tracks in UI Frame,
Lower.
4. Fix the J-Rails / Wagon to the UI Frame, Lower by using 6x
screw M4x8 and washer, flat 4.3mm (7), torque: 2,3 Nm.
5. Connect the grounding cable, Cable, GND, A/N Drawer to
the UI Mtg. Fork by use of nut M6 w/lock and washer tooth
6.4 between cable shoe and UI Mtg. Fork, torque: 5.7 Nm.
6. Install the A/N Keyboard.