Use And Care Manual

10 Owner’s Manual for 34 Ton Log Splitter
General Information and Setup
Installing the Tow Bar
Figure 2-5. Parts Supplied in Hardware Kit #2
NOTE: Install the washers with one washer against the
head of the bolt, and the other washer against the lock-
nut.
1. See Figure 2-6. Remove pin and hitch clip (C)
locking jack stand (D) in place. Rotate jack stand
downwards and secure with pin and hitch clip.
Figure 2-6. Trailer Components
2. Secure rear of the tow bar to the reservoir assem-
bly (A) using two M10 x 80 bolts, four flat washers,
and two locknuts (B). Tighten hardware.
NOTE: In the next step, the horizontal beam lock (F)
must be installed with the handle (E) on the right side.
The slot in the beam bracket will only latch properly to the
handle if it is installed this way.
3. Install the horizontal beam lock onto tow bar using
two M10 x 80 bolts, four flat washers, and two lock-
nuts. Tighten hardware.
Installing the Pump Assembly
Figure 2-7. Parts Supplied in Hardware Kit #3
NOTE: O-rings in hardware kit #3 are used in Installing
the Hydraulic Hoses. Set o-rings aside in a secure
place until needed.
1. Remove engine from container and place on a
level surface.
2. See Figure 2-8. Slowly pull on engine starter cord
to position key slot (A) at top of shaft.
Figure 2-8. Key Slot Position
3. Gently tap the key (located in parts box) into the
key slot on engine shaft using a soft face hammer.
Parts Supplied in Hardware Kit #2
Item # Description Qty
1 Horizontal beam lock 1
2 Bolt, hex, M10 x 80 4
3 Washer, flat, M10 8
4 Nut, nylon lock, M10 4
006538
1
2
3
4
006539
A
B
C
D
B
E
F
Parts Supplied in Hardware Kit #3
Item # Description Qty
1 Two stage pump assembly 1
2 Bolt, HCS, M8-1.25 x 30 in 4
3 Washer, lock, M8 4
4 Washer, flat, M8 4
5 O-ring, 11 mm x 2 mm 2
6 Keyway, 1/4 in, Square 1
006540
1
2
3
4
5
6
006541
A