User Manual
Table Of Contents
- IMPORTANT
- Legal Terms Governing This Document
- 1 OVERVIEW
- 2 PRE-INSTALLATION
- (Step 3) MOUNTING THE NODE B BRACKET
- 4 Site Preparation for Node B Installation
- 5 (Step 10) PHYSICAL INSTALLATION OF THE NODE B
- 5.1 Placing the Node B into the Rack
- 5.2 Service Area Interfaces
- 5.3 (Step 6) Grounding Installation and Inspection
- 5.4 Cable Clamp Seal
- 5.5 Connecting Power to the Node B
- Backhaul Connections to INC
- 5.7 Alarm Connections
- 5.8 Replacement of the Seal cable clamp
- 5.9 Conduit Pivot Bracket Securing
- 5.10 Closing the Door and securing the NodeB
- 5.11 GPS
- 6 (Step 11) Power up and Initial Setup of Node B
- 8
- 8 (Step 12) SOFTWARE INSTALLATION
- 9 (Step 13) On Air final check
- 10 Operation & Maintenance
Node B Installation Guide
DRAFT
17 July, 2001 IPWireless Proprietary
IT IS ILLEGAL TO MAKE COPIES OF THIS DOCUMENT WITHOUT EXPRESS PERMISSION BY IPWIRELESS
12
3.1 WALL MOUNT
W
ALL
M
OUNT
A
SSEMBLY
General Safety Precautions:
• Wall construction is able to support the weight of the unit assembly.
• Proper grounding
3.1.1 Mounting Considerations
Consider the earthquake zone requirements for the given site being considered. Ensure that the
mounting location complies with these considerations.
Review the GPS installation guidelines to ensure that the location will allow proper operation of
the Node B. I.e. a Southern Exposure is required for outside installations and a remote GPS
antenna or GPS repeater will be necessary in areas without a southern exposure or indoors.