4.3 (Step 7) GPS
For proper operation of the GPS receiver, the Node B must have a clear southern view of the sky.
A site survey should be done before Node B installation to verify that the Node B installation
location is suitable for GPS reception. A simple survey method is to take a handheld GPS
receiver to the site and verify that GPS lock is obtained in the location of the Node B installation.
The handheld GPS should be able to obtain a “locked” condition within 2 minutes of power-on,
and should be able to see a minimum of 4 satellites at all times. Note that when the Node B is to
be installed on or near a tower or building wall, the GPS survey should replicate this
configuration exactly.
4.4 Service Cover Area
The following figures illustrate the key elements for reference in the cable interface service area
of the NodeB.
Mains Supply
Safety cover
RJ45 Cable Clamp
Alarm
Cable Clam
p
Seal Cable Clam
p
7 Segment Display