Instructions / Assembly

Eave Drip on Rake applied
over underlayment
Eave Drip on Eave applied
directly to the roof deck
Trim and bend
Eave Drip on
corners to form
a box end
GALVANIZED EAVE DRIP
INSTALLATION GUIDELINES
These installation guidelines are for use with typical or standard applications. It is always recommended to seek advice from a licensed professional,
and to check with your local building inspector or building permit office for approvals and possible variations that may apply.
CAUTION!
Working above grade is inherently dangerous, be sure that proper fall protection measures are in place.
When working with power tools and sheet metal, gloves and eye protection are absolutely required.
Begin installation along the eaves, starting at a corner and working your way
around, overlapping each succeeding piece of drip edge by 2-3 inches.
After the eave drip edge has been installed, apply the underlayment and/or
ice-water barrier.
Once the underlayment has been installed, apply the drip edge to the rakes.
Make box corners by wrapping the rake edge around the eave metal.
Depending on local building codes and wind conditions, roof edge should be
nailed every 4 in. - 24 in.
1/32"
Over Driven