Installation

Determining the Rough Opening “R.O. Dimension
Framing in new construction should follow these dimension.
Standard 2x4 studs and 1/2” sheetrock are shown in the illustrations.
For 6” deep models a semi-recessed application is necessary.
4” & 6” deep cabinets
Model Number Rough Opening Single Width Tiered Cabinets
Width Height
R-VTS-16-54H 14 3/8 54 3/16”
R-VTS-16-60H 14 3/8” 60 3/16”
R-VTS-16-66H 14 3/8” 66 3/16”
R-VTS-16-72H 14 3/8” 72 3/16”
R-VTS-20-60H 18 3/8” 60 3/16”
R-VTS-20-66H 18 3/8” 66 3/16”
R-VTS-20-72H 22 3/8” 72 3/16”
R-VTS-24-60H 22 3/8” 60 3/16”
R-VTS-24-66H 22 3/8” 66 3/16”
R-VTS-24-72H 22 3/8” 72 3/16”
6” deep cabinets may be installed fully recessed where 2x6 studs are used or
semi recessed with standard 2x4 studs. Special side mirror kits are available for
semi recessed installations.
3
Tools Required for Installation
GlassCrafters recommends the following tools to prop-
erly and safely install your Mirrored Cabinets.
A. Safety Glasses -- should be worn at all times
B. Tape Measure
C. Level
D. #2 Phillips Head Screw Driver
E. Power Screw Driver
F. Electric Drill
G. 8mm 3/16” Masonry Drill Bit
H. 7/32” Drill Bit
I. Non Ammonia Household Glass Cleaner
J. Soft Paper Towels
Single Cabinet width “R.O.” Rough Opening formula:
Overall cabinet width less 5/8” = Rough Opening
Example: Model R-VTS-16 = 15” overall width less 5/8” = 14 3/8” R.O. width.
Example:
Two (2) 30” height cabinets = 60” + 3/16” = 60 3/16” R.O. Height
Rough Opening Height: overall cabinet height + 3/16” = R.O. Height.
Important: Make sure you allow for a
minimum of 1” clearance above or below any
obstructions to the door swing such as:
at the top -- light xtures; and
at the bottom baseboard trim, cabinets &
heating elements.
Rough Opening:
Note: Cabinet installs over nished wall with
sheetrock and/or tile nishes completed. 3/4”
Flange on all sides of the cabinet will cover
the remaining space in the R.O.