Installation Guide

E N G L I S H
E N G L I S H
ROOF WIDTH
SLAB WIDTH
ROOF
DEPTH
SLAB
DEPTH
SLAB DIMENSIONS
100mm
100mm
Diagram A
Determine size of
concrete slab
by adding 100mm to width
and 100mm to depth of
roof size of shed.
(See Diagram A)
A
Make sure slab area is square by ensuring
diagonal corner dimensions are equal. (Diagram B)
B
MEASUREMENT 'X' = MEASUREMENT 'Y'
SLAB
AREA
X
Y
Y
X
Diagram B
FORMWORK
BUILDERS
PLASTIC
Diagram D
D
Lay builders plastic on ground as barrier to rising moisture. (Diagram D)
Formwork must be100mm thick and level. (Diagram C)
C
Diagram C
FORMWORK
SPIRIT LEVEL
This page shows recommended method and dimensions. Make sure site is firm and level, and water drains away from site.
SHED REQUIRES A SOLID FOUNDATION.
FORMWORK
FORMWORK
F52 REINFORCING
STEEL MESH
MESH RAISED TO
APPROXIMATELY HALF
THICKNESS OF FORMWORK
F52
REINFORCING
STEEL MESH
Diagram E
E
Place F52 reinforcing steel mesh on top of builders plastic, ensuring steel mesh is raised off plastic to
depth of approximately half thickness of formwork. (Diagram E). Pour concrete. Allow five days to cure.
7
GB
BA
BA
GB
B O S A N S K I
B O S A N S K I
DIMENZIJE PLOČE
100mm
100mm
A
B
X
Y
Y
X
SLIKA D
D
C
SLIKA C
SLIKA E
E
ŠUPA ZAHTIJEVA ČVRSTE TEMELJE.
Ova stranica prikazuje preporučene metode i dimenzije. Podloga mora biti čvrsta i ravna, I odvodnja mora biti s tog mjesta.
ŠIRINA KROVA
ŠIRINA PLOČE
SLIKA A
DUBINA
KROVA
DUBINA
PLOČE
Odredite veličinu betonske
ploče dodavanjem
100mm na širinu 100'mm
i 100mm na dubinu veličine
krova šupe.
(Vidi sliku A)
Provjerite da li je ploča kvadratnog oblika tako da dimenzije
dijagonalnih uglova moraju biti jednake (Slika B)
MJERENJE “X” = MJERENJE “Y”
SLIKA B
POVRŠINA
PLOČE
Oplata mora biti debljine 100mm i ravna. (Slika C)
LIBELA
OPLATA
OPLATA
OPLATA
OPLATA
PVC ZA
GRAĐEVINARSTVO
Postaviti građevinski PVC na podlogu kao prepreku za dizanja vlage.
(Slika D)
F52 ČELIČNA
ARMIRANA MREŽA
F52 ČELIČNA
ARMIRANA MREŽA
MREŽA PODIGNUTA ZA
OTPRILIKE POLA DEBLJINE
OPLATE
Postaviti F52 čeličnu armiranu mrežu na pvc , tako da čelična mreža bude podignuta iznad pvc-a za oko
pola debljine oplate. (Slika E). Naliti beton. Ostaviti 5 dana da se stvrdne.
© Globel Industries Pty Ltd GI00053 August 2021