User's Manual

Walgreens Installation Guide
G-1-2002-2B
Walgreens Installation Guide 2B.doc
Use or disclosure of this document is covered under the Non-Disclosure Agreement executed between the reader and Goliath Solutions,
LLC. This document and the information contained herein are privileged and should only be viewed by expressly authorized parties.
5/27/2008 Page: 3-4
Quality Assurance Survey:
Shortly after the completion of the installation a GOLIATH Employee or a designated
representative of GOLIATH Solutions will visit the installed store and perform a Quality
Assurance Survey. The Surveyor will use the QA Checklist found in Appendix
B – Support Documents during this visit. The purpose of this visit is to complete the
following tasks:
1) Verify that the Store Management was satisfied with the installation and the
performance of the CIT team. This would include but is not limited to:
The Store Management’s evaluation of the installation and the CIT team.
The quality of the installation.
Did the CIT team clean up all the debris from the installation?
Were all ceiling tiles reinstalled correctly after the completion of the installation?
If ceiling tiles were damaged during the installation, were they replaced
promptly?
2) Inspect the installation and verify that it has been completed to the standards
defined in the Walgreens Installation Guide. This would include but not limited to:
Equipment has been installed in the correct locations.
Were any antennas placed over fixtures or display tables and don’t have a
clear line of site to the floor.
The coaxial cable has been run through the ceiling according to the defined
standards.
The cables are not attached to or touching any structures in the ceiling, such as
threaded support rods and water pipes that are violations.
Service loops are present at the defined locations and meet the required
standards.
Antennae have been installed correctly according to defined standards.
The ceiling grid in the store has be correctly label with the location of the
Rx/ARA antennae.
Cables have been labeled appropriately.
The MEU is installed correctly and securely at the correct location.
The system is functioning correctly.
Verify that installation debris in the ceiling has been cleaned up.
3) Document any installation violations. Pictures to document the violations will be
taken if possible.