Chapter 4 - Store Installation Procedures:
Overview of the Installation Process:
The store installation process involves the installation of the transmitters (Tx/ATA),
receivers (Rx/ARA), coaxial cables and the MEU into the ceiling of a Retail Store. The
process will also include the installation of the CMU at the communications LAN cabinet in
the store if MEU III is being installed. The exact installation requirements and processes
for each Retailer are defined in the Cable Installation Guide for that Retailer.
The following list is a summary of the Installation Steps for the Goliath Solutions System.
1) Check-in with Store Management and the Help Desk.
2) Perform a Pre-installation Survey.
3) Installation Prep.
4) Installation of the CMU.
5) Temporary installation of one or more MEU’s for communications testing.
6) Cable Pulls.
7) Installation of Transmitters.
8) Installation of Receivers.
9) Permanent installation of the MEU’s.
10) Installation Completion.
11) Site Clean-up.
12) Store Check Out.
A brief summary of each step follows in this Guide and the Retailer Specific step is defined
in the Cable Installation Guide for that Retailer.