Check-In:
The Store Check-In process involves the following tasks:
Introduce yourself and your installation team to the highest available level of Store
Management.
Give an overview of the installation process.
Locate the Installation Kit shipped to the store.
Call the Help Desk to check-in.
Pre-installation Survey:
The Pre-installation Survey Process has two purposes. The first is to determine if there
are any issues that could prevent the successful installation of the GOLIATH System. If
there are no issues that would prevent the installation then the survey would determine the
correct locations to install the system hardware.
Some issues that could prevent the successful installation are
Missing Installation Kit.
Incomplete Installation Kit.
Damaged Installation Kit.
Not having the correct ladders or scissor lifts to get in the ceiling.
Obstructions in ceiling.
Non-Standard ceilings.
During the Survey you will determine the permanent location for the following hardware:
Determine the most suitable location for the CMU (if applicable).
Determine the most suitable power source location for the permanent MEU
installation location.
Determine the most suitable permanent location for the MEU.
Determine the antennae location (both Tx/ATA and Rx/ARA).