Installation Completion:
After the completion of the installation of the GOLIATH hardware in the store the following
tasks still must be completed:
Verify that all cables are securely connected to the MEU at their corresponding ports.
After all the antennas are connected to the MEU, connect the power to the MEU and
verify that the Green power indicator is on.
Site Clean-up:
Inspect the entire store, including the Stock Room, for any installation debris left by the
Crew.
If the location of the equipment was marked on the floor, remove the painters tape.
If there is a drop down ceiling verify all ceiling tiles are back in place and seated
properly.
If there is a drop down ceiling remove any debris from the drop-ceiling around the
MEU.
Dispose of the installation debris and trash.
Store Check-out:
You can check-out with the store management and the Help Desk after the following tasks
have been completed.
Completion of the System Test
Replace the ceiling tile at the MEU.
Gather all remaining installation equipment and remove it from the store.
Any OBF equipment should be boxed up with the return label and then sent to Goliath
Solutions.
Quality Assurance Survey (QA):
A QA Survey will be performed by GOLIATH personnel sometime after the installation.
The purpose of this visit is to verify that the CIV has completed the installation in
accordance with the standards and Best Practices specified in the agreed upon RFP and
this document.