GC9S96 Service Manual

SYSTEM OPERATION
15


































3”-24” BETWEEN PIPES

.












-
tween joist spaces. If the vent pipe must go below a joist and
then up into the last joist space to penetrate the header, two
45° elbows should be used to reach the header rather than
two 90° elbows.

Direct vent installations require both a combustion air intake

exit through the side of the building or run vertically and
exit through the roof of the building. The pipes may be run
through an existing unused chimney; however, they must
extend a minimum of 12 inches above the top of the chim-
ney. The space between the pipes and the chimney must

-
tions must be in the same atmospheric pressure zone. Refer
to Vent/Flue and Combustion Air Pipe - Termination Loca-
tions or Concentric Vent Termination section in this manual
-
tion construction.