SERVICING
71
To exit an equipment submenu and revert back to the
equipment menus, touch the Menu key. Touch Menu again
to revert back to the Thermostat Options Menu. Touch the
Run Schedule key to step out of all menus and back to the
CT thermostat Home Screen Display.
S-4 CHECKING TRANSFORMER AND CON-
TROL CIRCUIT
HIGH VOLTAGE!
Disconnect ALL power before servicing
or installing. Multiple power sources
may be present. Failure to do so may
cause property damage, personal injury
or death.
A step-down transformer (208/240 volt primary to 24 volt
secondary) is provided with each indoor unit. This allows
ample capacity for use with resistance heaters. The out-
door sections do not contain a transformer (see note be-
low).
NOTE: ComfortNet
TM
ready condensing units may have
an optional 240VAC to 24VAC transformer installed. This
transformer provides 24VAC power to the unitary (UC) con-
trol in some communicating system installation scenarios.
WARNING
Disconnect ALL power before servicing.
1. Remove control panel cover, or etc., to gain access to
transformer.
With power ON:
WARNING
Line Voltage now present.
2. Using a voltmeter, check voltage across secondary
voltage side of transformer (R to C).
3. No voltage indicates faulty transformer, bad wiring, or
bad splices.
4. Check transformer primary voltage at incoming line
voltage connections and/or splices.
5 If line voltage available at primary voltage side of trans-
former and wiring and splices good, transformer is
inoperative. Replace.