User Manual
56 GMC-I Messtechnik GmbH
❑ Suppressing Test Steps
Depending on the selected test standard, some of the following
test steps can be suppressed:
1
Before switching line voltage to the device under test, a short-circuit test
is conducted regardless of this setting.
❑ Setting Measuring Parameters for Individual Test Steps
Depending on the selected test standard, some of the following
test steps can be selected:
❑
Select between single and multiple measurement for individual test steps
❑
Set measurement duration of individual test steps (as of firmware 1.5.0)
Testing time for the respective measurement can be influenced
with these parameters. If a test step for a single measurement is
involved, the entire test step has a duration of the time entered in
seconds. If a test step for a multiple measurement is involved, the
measurement duration for each measuring point is influenced.
If 0 seconds is selected, continuous measurement is conducted
which can only be ended by pressing a key.
1
For measuring sequence VDE 0701-0702-PRCD with the following set-
ting „PRCD type: PRCD (SPE)“ the measurement duration cannot be in-
fluenced.
The measurement duration which has been set in this case only affects
the RPE measurement with PRCD types „PRCD (standard)“ and
„PRCD-S (SPE)“.
Parameter Suppressible test steps
Visual Inspection Visual Inspection
Function test Function test
RPE Protective conductor resistance test
RISO PCI+II Insulation resistance tests for PCI and PCII
RISO pri./sec. Insulation resistance test between the primary and
secondary sides of PCIII DUTs
RISO sec./PE Insulation resistance test between the secondary side and
PE of PCIII DUTs
RISO BF/CF
(IEC 62353)
Insulation resistance tests at BF/CF application parts
RISO welding circuit
(IEC 60974-4)
RISO tests between the primary side and the welding
output, as well as between PE and the welding output
Reversed polarity
All leakage current measurements with reversed polarity
IPE measurement type
(active)
Protective conductor current test
IB
Touch current test
IB welding circuit
Touch current test at welding circuit
Display test instructions
Test instructions which are not necessarily required for experi-
enced inspectors
Short-circuit test L-N Short-circuit test between L and N
1
Short-circuit test LN-PE Short-circuit test between LN and PE1
1
Open-circuit voltage
(IEC 60974-4)
Open-circuit voltage at welding unit
Continuity test
(VLTG test only)
Continuity test with EL1/VL2E/AT3-IIIE adapter
PCIII supply voltage Supply voltage measurement (for PCIII DUTs; only for
measurement type „Active“)
Parameter Meaning
RPE IP Select test current for protective conductor resistance test:
200 mA AC, ±200mADC or 10AAC
(only with SECUTEST BASE10/PRO or feature G01)
IPE measurement type
(active)
Select measurement type for protective conductor current
measurement for active device testing (differential/direct)
IG measurement type
(active) (IEC 62353)
Select measurement type for device leakage current
measurement for active device testing (differential/direct)
Parameter
(as of FW 1.5.0)
Meaning
RPE as
Switch the “protective conductor resistance” test step back
and forth between multiple and single measurement
Parameter
(as of FW1.8.0)
Meaning
RISO SK II as Switch the insulation resistance measurement at PC II
parts (measurements at applied parts/welding outputs are
not affected) back and forth between multiple and single
measurement
IB as Switch the touch current measurement back and forth
between multiple and single measurement
IB SK II as (IEC 60974 only) Switch the touch current measurement
at PC II parts back and forth between multiple and single
measurement
Parameter
(as of FW 1.5.0)
Meaning
RPE measurement
duration
1
Set testing time for the protective conductor resistance
measurement (0 to 60 seconds)
IPE measurement
duration
Set testing time for the protective conductor current
measurement (0 to 60 seconds)
IG measurement
duration
Set testing time for the device leakage current measure-
ment (0 to 60 seconds)
Parameter
(as of FW1.8.0)
Meaning
IB measurement
duration
Set testing time for the touch current measurement
(0 to 60 seconds)
IB SK II measurement
duration
(only for IEC 60974) Set testing time for the touch current
measurement at PC II parts (with the exception of welding
outputs) (0 to 60 seconds)
RISO SK II measurement
duration
Set testing time for RISO measurements at PC II parts
(0 to 60 seconds)