User's Manual

Setup
3A2175A 29
Setup
Perform this setup procedure to secure all necessary
machine connections for machine operation.
1. Locate HFR.
a. Locate HFR on a level surface. See Dimen-
sions on page 94 for space requirements.
b. Do not expose HFR to rain.
2. Electrical requirements. See Models on page 4
for detailed electrical requirements information.
3. Connect electrical cord.
NOTE: See Power Line Voltage Surges information on
page 30.
NOTE: Power cord is not supplied. See the following
table.
Residual Current Device (RCD) must be rated at
300 mA if installed.
Electrical Cord Wires by Model
230V, 1 phase: L1, L2, GND
400V, 3 phase: L1, L2, L3, N, GND
Use 5/32 or 4 mm hex allen wrench to connect the two
or three power leads to L1, L2, and L3, as applicable.
Connect green to ground (GND).
Electrical Cord Wires by Model
230V, 1phase: L1, L2, (L3 - No Connection), GND
400V, 3 phase: L1, L2, L3, N, GND
NOTICE
To avoid machine damage and personal injury,
ensure the machine is securely strapped to the pallet
to prevent tipping before lifting.
Installing this equipment requires access to parts
which may cause electric shock or other serious injury
if work is not performed properly. Have a qualified
electrician connect power and ground to main power
switch terminals, see step 3 in this setup procedure.
All electrical wiring must be done by a qualified electri-
cian and comply with all local codes and regulations.
Table 1: Power Cord Requirements
Model
Cord Requirements
AWG (mm
2
)
230V, 1 phase 6 (13.3), 2 wire + ground
400V, 3 phase 6 (13.3), 4 wire + ground
FIG. 11: 230V, 1 phase shown
FIG. 12: 400V, 3 phase shown
FIG. 13: Grounding Lug
L1 L2 L3
L1 L2 L3N