2. Installation
PNEG-1614 Heavy Duty Bin Stairs and Platform Assembly for 2.66" Corrugated Bin 19
3. After installing the top handrails, the intermediate handrails can be put into place. They will use
the top hole in the middle of the handrail post with 5/16" x 1-1/4" bolts and nut. (See Figure 2S on
Page 17.) The large tube should be placed on the upper handrail post and the small tube should
be slid into it and placed on the lower handrail post. The very top intermediate handrail connecting
the platform to the first post may need to be shortened. Equal amounts should be cut from both of
the handrails.
Figure 2W Intermediate Handrail
5/16" x 1-1/4" Bin
bolt and nut
Small intermediate
handrail (LDR-4088)
Large intermediate
handrail (LDR-4087)