2003 Top Dry Service School
TOP DRY PLENUM HI LIMIT INSTALLATION
1.
Assemble two pieces of conduit together with coupler.
2.
Mount conduit clamps to conduit assembly.
3. Locate conduit assembly on the bottom of a rafter at least 2 feet to one side of the fan
entrance. Do not install between two fan entrances.
4.
Mark bin wall where conduit will pass through and drill a hole just large enough to allow the
conduit to pass through. Seal this with caulking when complete.
5. Install white PVC box assembly on outside of bin wall.
6.
Insert 10’ capillary into conduit assembly.
7.
Connect SJO cord to hi limit and connect wires to terminals 20 and 21 on the master fan
terminal strip. These terminals are J7-08, and J7-03.