User guide
48 PNEG-1708 GSI Modular Tower Dryer
9. Burner/Blower Module - Special Considerations
1. Before lifting and stacking modules, be sure the floor planks are installed for the burner/blower
module. These should be factory installed. The burner/blower module contains flooring to support
the user when entering the dryer to perform cleaning or maintenance duties.
The flooring planks for the burner/blower module are similar to catwalk planks but have “TABS” on
the ends to drop into slots in the burner/blower module. (See Figure 9A.)
Figure 9A
In Figure 9A, one plank has been placed. Note the longer planks will be placed to the outside (closer to
the dryer wall) and the shorter planks to the inside (closer to the burner/blower).
In Figure 9B, multiple flooring planks have been installed along the outer portion (closer to the dryer wall).
The inner planks have yet to be placed.
Figure 9B