User guide

10. Lifting and Stacking the Modules
54 PNEG-1708 GSI Modular Tower Dryer
Recommended Stacking Order: Model 1200 Series Dryer
Figure 10C Model 1200
Step 1:
Stack and connect
Roof to Module 6
Step 2:
Stack and connect
Roof/6 to Module 5
Step 5:
Stack and connect
Module 2 to Base
Step 6:
Stack and connect
Roof/6/5/4/3 to Base/2
Base/UnloadBase/Unload
Step 4:
Stack and connect
Roof/6/5/4 to Module 3
This suggested sequencing plan maximizes safety and convenience, by performing
most work close to the ground.
IMPORTANT: Make sure crane is of adequate lifting capacity. The recommended strap length is 6' long.
NOTE: Catwalks, ladders and other accessories not shown for clarity. Be sure to include weight of accessories
when combining modules.
NOTE: If the crane is not sufficient to lift the combined weight of
Roof/6/5/4/3 as shown, replace step 4 with connecting Modules 3 and 2,
stacking 3/2 on the base and then placing Roof/6/5/4 on top of base/2/3.
Step 3:
Stack and connect
Roof/6/5 to Module 4