Installation Guide

EZ Metal Roof Mount
Attachments
10 of 12
Installation Instructions:
EZ Metal Roof Mount Kit K20051-XXX
1. From the marked location drill the pilot hole for the Lag
Bolt with a 7/32” drill bit. For maximum strength, the hole
should not be more than 3 in depth, and a drill stop may
be used to insure this.
2. To ensure a strong and water tight seal, wipe away
excess grease or debris from the mounting location. Fill
pilot hole with sealant, such as ChemLink DuraLink for
metal roofs. Install AL Shoe to Metal Roof by using 5/16
Lag Bolt. Tighten to 25 ft. lbs. torque.
3. Install L-Foot to AL Shoe and lightly hand tighten Hex
Cap.
4. Install AL Rail to L-Foot to the specific orientation. Then,
tighten 3/8 Flange Nut to 15 ft-lbs. and Hex Cap to 15 ft-
lbs. torque.
2
4
1
3