Use and Care Guide

INSTALATION
SOIL PREPARATION:
1. Any rigid element like sidewalks, walls, concrete edges, etc. must be done before grid
system installation.
2. Preparation consists on removing all soft soil like plant soil and level it the best possible,
compact loose soil if needed. Leave enough deep space to place gravel base and grid
(gravel base thickness depending on paving use) plus 2 inches for the Premium P40 grid
or 1.5 inches for the Slim S56 grid.
GRAVEL BASE:
1. There has to be a base made of gravel between soil and plastic grid. It will help finish
leveling the soil in case there are some imperfections, also it will give all the system a
higher weight capacity and retain more rain water for absorption.
2. Base thickness depends on the type of project. It is recommended to be from two to ten
inches thick.
a. A two to four inches base should be made for walking path, patio, park or any
place where there is not going to be cars (Slim S56 grid).
b. A eight to ten inches base is recommended for places where there is going to be
cars or trucks. Four inches thick base for house driveways and ten inches thick
for parking lots and low traffic streets (Premium P40 grid).
3. Base gravel should be made with angular clean stone. It can go from 3/4 to 1 1/2 inches
diameter. Level and compact gravel base the best way possible.
GRID INSTALLATION:
1. Grid should be confined all around within a wall, side walk, concrete edge, etc,
previously made.
2. Having ready gravel base just place the grid above and assemble it together. It is
important to have an idea which way you are going to accommodate the grid to avoid
waste specially within irregular areas.

Summary of content (2 pages)