Check Items for Test Run
Put check mark in boxes
No gas leak from linesets?
Are the linesets insulated properly?

inserted to the terminal block?

Is condensate draining correctly?
Is the ground wire secure? Is the indoor unit secured?
Is power source voltage correct according to local code?
Is there any noise?
Is the lamp normally lighting?
Are cooling and heating performing normally?
Is the operation of room temperature sensor normal?
Step 6 - Charging
Step 7 - System Test
 Using the OPERATING INSTRUCTIONS, explain to the user how to use the air conditioner (the remote controller, removing

operation, etc.)
 Recommend that the user read the OPERATING INSTRUCTIONS carefully.
Step 8 - Explaining Operation to the End User
Charge the system using the weight method.
The unit comes with enough charge for 25 feet per circuit.
For example, the 2 port unit will come with 50 feet of charge,
the 3 port unit will come with 75 feet of charge, and the 4
port unit will come with 100 feet of charge. If the system
must have additional charge added, add .2 ounces of charge
for every additional foot of refrigerant line that is above
factory charge. If the total of distance of the installed line

Simply release the charge by opening the system service
valves.