8
FLOOR LEVELING OPTIONS
Therearemultiplewaystolevelyouroorframe.Ourrecommendedlevelingmethodisshownbelow.
Leveling materials are not included in this kit.
•Levelunder4x4runnersonly.
•Locatelevelingmaterial12"fromendsofrunnersandnomorethan48"apart.
•Asphaltshinglesshouldbeusedbetween4x4runnersandblocksortreatedlumber.Neveruse
shingles in direct contact with ground.
•Forbestresultsandaidinginwaterdrainageusegravelundereachconcreteblock.
LEVELINGMETHODS
•If you are building your shed on a concrete foundation see the following page.
CONCRETE
Useonlywoodtreatedforgroundcontactandfastenersapprovedforusewithtreatedwood.
Alwayssupportframeseams.
Levelinghigherthan16"notrecommended.
LEVELINGMATERIALS
Gravel
2x4 Treated Lumber
Solid Masonry Blocks in 1", 2", 4" or 8" thickness
Asphalt Shingles
8" Block
4" Block
Gravel
Gravel
Do not exceed 16".
4x4 Runner
Shingle
Shingle
Maximum between leveling
material locations.
48"
12"
2x4 Treated Lumber
2" Block
Level
12"
PREFERREDMETHOD-4x4TREATEDRUNNERS
•3"Screwsangledinto4x4.
•(2)ateachpointframe
and 4x4 touch.
MATERIALREQUIRED
x2
4 x 4 x 10' (10 x 10 x 304,8 cm) Treated Lumber
FastenersforFrameto4x4.
(3"Screwsshownasoneoption.)Minimum(40)3"screws/exteriorgrade.
Measurementsto
centersof4x4's.
12"
(30,5 cm)
12"